Tasklist End
Provide Fuel PO # and sign and obtain copy of fuel receipt if fuel taken Links: Local file
(end of leg 3 ask engineer for remaining fuel report (tank soundings)
CATCH computer - Run catch entry program for checking data; MAKE APPROPRIATE EDITS! Links: Local file
WHEELHOUSE/CALYPSO computer - Use DB_Utilities to make 7zip file (remaining or fixed hauls) and SFTP to Seattle DB Links: Local file
Deck Lead or designee does line-by-line edit of catch data for each leg
Deck Lead or designee obtain electronic table of crab weights and numbers from Crab Lead and reconcile with those in DATA_ENT
Deck Lead or designee obtain electronic table of Halibut catch numbers and lengths by haul from IPHC Biologist and reconcile with those in DATA_ENT
HAND CARRY Thumbdrive and/or hard copies back to Seattle (FPC, Deck Boss, or designee)
Leg data sheets (HAULFORM, Wheelhouse Haul Rept, DATA_ENT Catch and Length Reports (mandatory), ES60 LOG SHEETS) and hand carry to Seattle
WHEELHOUSE/CALYPSO computer - Make copies of all BTD, BTH, BC2, and MARP files Links: Local directory
WHEELHOUSE/CALYPSO computer - Use DB_Utilities to back-up WHEELHOUSE DB Links: Local file
**WHEELHOUSE/CALYPSO computer - Make copy of DDMMYYYY*.DMP and exp_python.log files from C:/oracle_data_pump_files directory** Links: Local directory
MARPORT computer - Make copy of C/:Program Files/Marport Server/Logs directory (BVDR files) Links: Local directory
CATCH computer - Make copy of DATA_ENT.MDB program in C:/data directory Links: Local directory
CATCH computer - Add metadata to photos and make copies of Portfolio DB and Photos from leg directory (C:/Data/Photos) Links: Local file
CATCH computer - copy Length and Specimen App CSV files from bluetooth directory (C:/Users/NOAADATA/Documents/Bluetooth/inbox) Links: Local directory
GLOBE computer - Make copy of Globe track data files (C:/Globe/Tracks/) Links: Local directory
**GLOBE computer - Make copy of Globe log data files (C:/Globe/Log/2022/*.glg)** Links: Local file
LAST LEG FPC: Remove GLOBE dongle, place in envelope WITH INSTALLATION SOFTWARE, hand-carry back to Seattle, and return directly to group supervisor
CTD Computer - Make copy of CTD data files
ES60 computer - take back-up and regular hard drives back to Seattle (also take POWER SUPPLIES and USB connectors for hard drives at end of survey) Links: Local file
Copy of fuel receipt to RACE Directorate
Completed forms from FPC filebox
Completed Ergonomic Reporting forms sent back To Rich Koster (Richard.Koster@noaa.gov)
Checklist for bundling and stacking a net Links: Local file
OSI 2021 Job Service No’s Links: Local file
Any equipment being kept in Dutch Harbor for another cruise should be inventoried and the inventory list brought back to Seattle
Contact shipping company to pick up loaded container(s) for southbound voyage. GBL(s) will be with RSST or Kevin Godfrey. Vessel should also have digital PDF copy of GBL.
ES60 Calibration (end of last leg) Links: Local file
Collect all boots and rain gear loaned to interns and others as they depart the vessel
Freshwater rinse all metal tools and parts (bolts, washers, nuts etc.) that have been on deck and exposed to saltwater.
Empty the eyewash bottles as one of your last items; ship them home empty.
Otolith trays: Otolith trays
Otolith trays: caps tightened
Otolith trays: trays scrubbed with dilute bleach solution
Otolith trays: trays dried
Otolith trays: Pollock otoliths packaged and shipped after each leg (EBS SHELF) Links: Local file
All deck tables scrubbed and pressure washed
Baskets and white totes scrubbed or pressure washed and stacked
Electronic scales: cleaned and scrubbed
Electronic scales: rinsed with fresh water
Electronic scales: dried and packed
Deck supplies cleaned
Ethanol and formalin buckets capped with uncut lids and buckets properly labeled Links: Local file
Frozen specimens put in freezer boxes, properly labeled and sealed with tape and shipped
Preserved specimens in buckets: Take properly sealed and labeled stomach buckets to Coastal Transportation for shipment. Links: Local file
Record the quantity of packages associated with each project and email or deliver that information to the Special Projects Coordinator
Remaining ethanol and formalin properly stored and labeled Links: Local file
Document conditions for vessel ingress and egress
Chemical storage cleaned and rinsed thoroughly and chemicals returned Links: Local file
Office supplies packed in gray boxes
Office and bridge computers and printers disassembled and packed in proper boxes
All bedding and pillows stuffed in trash bags labeled USED and packed in van
All tools cleaned and replaced in their proper case and location
On deck Invert and Fish guides cleaned and dried
State rooms cleaned, trash removed, and floor vacuumed (each leg!)
All items removed from the bridge/house including antennas, signs, wiring, etc. (leave MR350 GPS pucks mounted on vessel)
RACE survival suits, PFD’s and hard hats removed from vessel and OSI storage room and placed in the 40’ container
Net mensuration gear cleaned, disassembled and packed in cases
Pack only RSST items in RSST tote